Sinolam Smarter Energy

Project Progress

Advanced-stage energy development with significant progress in equipment manufacturing, site preparation, and infrastructure readiness.

The Sinolam Smarter Energy project demonstrates solid progress across both equipment manufacturing and on-site development, including land preparation, access infrastructure, and industrial platform readiness for the next construction phase.

0
%
Main equipment manufactured
0
Ha
Land area prepared
0
km
Temporary access road completed
0
M m³
Earthworks completed

Step1

Site Preparation Land clearing and initial works completed.

Access Infrastructure Temporary roads and logistics access developed.

Step2

Step3

Total of Excavated & Backfilled Material
9000,000 m³ (X 2)
1,800,000 m³.

Foundation Readiness Preparation underway for structural development.

Step4

Let’s build the right partnership Strategic connections that drive shared success

AREA FOR GTPP PROJECT DEVELOPMENT

TEMPORARY FACILITIES

Project Progress

Real-time construction status across both strategic site locations in Panama.

Site Option 1

Rio Alejandro
Energy Park
  • Tree cutting and site clearing works finished.
  • Temporary access road finished and final access road ongoing.
  • Site levelling works for both the Power Block and the Regasification Plant (Onshore part of the LNG Terminal) finished.
  • All preparation works are being carried out to start foundations in order to be ready before the equipment arrives at site.
  • Temporary facilities are finished for the Power Block, ongoing for the LNG Terminal site.

Site Option 2

Isla de Margarita
Marine Terminal
  • Sea-bed Concession obtained.
  • Sub-lease Concession obtained.
  • Pier construction in progress.