Sinolam Smarter Energy

Project Progress

Advanced-stage energy development with significant progress in equipment manufacturing, site preparation, and infrastructure readiness.

The Sinolam Smarter Energy project demonstrates solid progress across both equipment manufacturing and on-site development, including land preparation, access infrastructure, and industrial platform readiness for the next construction phase.

0
%
Main equipment manufactured
0
Ha
Land area prepared
0
km
Temporary access road completed
0
M m³
Earthworks completed

Step1

Site Preparation Land clearing and initial works completed.

Access Infrastructure Temporary roads and logistics access developed.

Step2

Step3

Total of Excavated & Backfilled Material
9000,000 m³ (X 2)
1,800,000 m³.

Foundation Readiness Preparation underway for structural development.

Step4

Let’s build the right partnership Strategic connections that drive shared success

AREA FOR GTPP PROJECT DEVELOPMENT

(Virgin Forest)

TEMPORARY FACILITIES

Project Progress

Real-time construction status across both strategic site locations in Panama.

Site Option 1

Rio Alejandro
Energy Park
  • Tree cutting and site clearing works finished.
  • Temporary access road finished and final access road ongoing.
  • Site levelling works for both the Power Block and the Regasification Plant (Onshore part of the LNG Terminal) finished.
  • All preparation works are being carried out to start foundations in order to be ready before the equipment arrives at site.
  • Temporary facilities are finished for the Power Block, ongoing for the LNG Terminal site.

Site Option 2

Isla de Margarita
Marine Terminal
  • Sea-bed Concession obtained.
  • Sub-lease Concession obtained.
  • Pier construction in progress.