Sinolam Smarter Energy
Project Progress
Advanced-stage energy development with significant progress in equipment manufacturing, site preparation, and infrastructure readiness.
The Sinolam Smarter Energy project demonstrates solid progress across both equipment manufacturing and on-site development, including land preparation, access infrastructure, and industrial platform readiness for the next construction phase.
0
%
Main equipment manufactured
0
Ha
Land area prepared
0
km
Temporary access road completed
0
M m³
Earthworks completed
Let’s build the right partnership Strategic connections that drive shared success
AREA FOR GTPP PROJECT DEVELOPMENT
(Virgin Forest)

TEMPORARY FACILITIES
Project Progress
Real-time construction status across both strategic site locations in Panama.

Site Option 1
Rio Alejandro
Energy Park
Energy Park
- Tree cutting and site clearing works finished.
- Temporary access road finished and final access road ongoing.
- Site levelling works for both the Power Block and the Regasification Plant (Onshore part of the LNG Terminal) finished.
- All preparation works are being carried out to start foundations in order to be ready before the equipment arrives at site.
- Temporary facilities are finished for the Power Block, ongoing for the LNG Terminal site.

Site Option 2
Isla de Margarita
Marine Terminal
Marine Terminal
- Sea-bed Concession obtained.
- Sub-lease Concession obtained.
- Pier construction in progress.